Track and asphalting works Rijswijkseplein
In June, the Municipality of The Hague and HTM will start extensive and long-term track and asphalting work on and around the Rijswijkseplein in The Hague. All trams passing Hollands Spoor Station will be diverted in 3 different phases.

Phase 1: from Thursday, June 4 to Friday, July 17
During Phase 1, work will be carried out on the tracks near the Zieken. All trams entering the city from Hollands Spoor station will be diverted via Weteringkade and Lekstraat. As a result, some stops in one direction will be cancelled. The trams will temporarily stop at other stops along the way. Hollands Spoor and Den Haag Centraal stations remain easily accessible. Please check the map for the routes of trams 1, 9, 10, 15, 16, and 17 in Phase 1.
Phase 2: from Saturday, July 18 to Sunday, August 16
Information regarding this phase will follow later.
Phase 3: from Monday, August 17 to Sunday, August 30
Information regarding this phase will follow later.
Asphalt and other works
Information about the asphalt and other works and accessibility in the area can be found at www.denhaag.nl/rijswijkseplein